Home > Planning > Regeneration > Townwall Street Underpass Improvement Project

Townwall Street Underpass Improvement Project

20240305_114957

 

Dover District Council image of underpass taken March 2024 

Project Progress 

June 2025 

The council has procured a main contractor for the project and works have now started on site. Works on the underpass include: 

- New bold and creative visuals on the walls with a 'Dover Time Tunnel' theme 

- Resurfacing of the footpaths and cycleways 

- Repainting of handrails, walls and ceilings 

- Renewing cycle lane markings 

- Replacing of broken tiles and drainage grills, and cleaning light fittings 

- Continued working with a range of partners to renovate and maintain the underpass for the future 

It is anticipated that the works to the underpass will be finished by the end of the year. 

Click here for the latest Dover District Council press release about the project.

Background 

In 2021, Dover District Council secured £3.2m Future High Street Funding and with £1.7m of matching funding from the Council has a total budget of £4.9m to:

  • To build a Creative Centre in Bench Street area of Dover
  • To improve the underpass on Townwall Street/A20

Since the award of the Future High Street funding, Dover District Council has been successful in its bid for funding from the Levelling up Fund. Therefore, the Creative Centre project will now be delivered as part of the Dover Beacon Project which brings together plans for a Creative Centre, Education Campus, and Business Centre into one iconic building on Bench Street, Dover, with improved public realm.

We have been talking to stakeholders about the Underpass Improvement project identifying areas of responsibility and the project scope.

We have reported flooding issues in the underpass to National Highways, which resulted in improvements to the pumps and flood systems in the underpass in 2023. There is ongoing maintenance requirement for National Highways to undertake to prevent flooding. We have been provided with a dedicated phone number and email address for members of the public to report flooding issues in the underpass. 

Telephone Number: 0300 1235000  Email address: info@nationalhighways.co.uk

Scope of the Project

The underpass structure is owed by National Highways and Kent County Council are responsible for walking and cycle paths, and the surface maintenance in the underpass. We have been consulting with National Highways, Kent County Council, Port of Dover and other important stakeholders about this project to look at what can be achieved to improve the underpass. Constraints to the physical fabric of the underpass mean it is important that any alterations do not affect the integrity of the structure. 

Consultation 2023

The Council undertook consultation in 2023 through in person events and an online survey about the proposed cosmetic improvements to the underpass using panel covers for the tiles. 

The consultation focused on the possibility of enhancing the existing tiles in the underpass with three conceptual themes. 

Combined results from consultation events and online survey showed 50% of all respondents favoured the Dover Time Tunnel (Selfie Bunker 27%, Refreshed Tradition 23%) as their preferred option.

During our consultation you also gave us some valuable feedback about the underpass and how you felt it could be improved. Whilst most of you welcomed the proposals to enhance the aesthetics you felt there were other things that also needed to be considered. 

  • Improvements to the lighting
  • Safety of the cycle route
  • Personal safety and use of CCTV
  • Review of the drainage to prevent further flooding 
  • Improvement to surface materials 
  • The potential for an at grade crossing over Townwall Street

For further details about the Underpass Improvement Project. Please see the frequently asked questions

 For the further details on the Creative Centre and the Dover Beacon Project please follow this link Dover Beacon Project .